Project Ashridge

Overview
Project Ashridge started as a single 1,325m² block in Darra, zoned low-medium density residential and carrying an older six-bedroom house. With rail, shops and services within walking distance, the site had the size and location to support far more than one dwelling. Dominion negotiated a reduced purchase price before going unconditional.
Dominion then lodged a 1 into 4 subdivision and secured approval in just 14 business days. The original house was removed and the block was re-titled into four lots, with driveway easements giving the two rear lots their own access. Turning one title into four created the platform for the whole project.
Four double-storey co-living dwellings were built across the new lots, each with five private micro-apartments, delivering 20 tenancies in total. Every apartment has its own ensuite, kitchenette and patio or balcony. Construction reached practical completion in September 2026, and half the apartments were leased within 10 days of opening.
The site that once earned around $500 a week as a single rental now generates approximately $7,700 a week, with an estimated completed value of $6.2m.
Main Features
PRIVATE SUITES:
Every micro-apartment has its own ensuite, kitchenette, built-in robe and private patio or balcony, giving tenants self-sufficient living with shared kitchen and laundry facilities on site.
FURNISHED PREMIUM:
All 20 apartments were delivered fully furnished, a turn-key living solution that drives rapid lease-up, tenant retention and the rental premium the asset commands.
SOLAR POWERED:
Rooftop solar on all four dwellings offsets energy costs, protecting an all-inclusive rent model and supporting yield stability.
FAST APPROVAL:
The 1 into 4 subdivision was approved by council in just 14 business days. Dominion's systemised planning process reduces holding costs and gets projects to construction faster.
RAIL ACCESS:
Around 800m from Darra train station, with shops and amenity within walking distance.
20 TENANCIES:
Four double-storey dwellings with five private micro-apartments each, on four newly titled lots.

Project Snapshot
Commercial Summary




















Development Details
PROJECT TEAM
Town Planners, Surveyors, Civil Engineers, Builders, Project Managers, Development Lender, Private Investor, Property Managers
TIMELINE
Site secured March 2024, subdivision approved June 2024, practical completion September 2026
SUSTAINABILITY FEATURES
Rooftop solar across all four dwellings, all-inclusive utilities.
LOCATION HIGHLIGHTS
- Located in Darra, QLD, around 800m from Darra train station and within walking distance of shops and amenity
- Approximately 19km by road to the Brisbane CBD, with direct rail access
- 14 dedicated on-site car spaces across 20 tenancies
- Half of the 20 apartments leased within 10 days of opening
- One title subdivided into four, with council approval in 14 business days
- Rent lifted from around $500/wk as a single house to approximately $7,700/wk across 20 apartments